Programmed road and pavement works
On this page
Each year, a number of Barnet's roads and pavements are selected for repair based on their condition. Our programme of works for 2025/2026 was agreed by Barnet Council's Cabinet on 5 February 2025.
Start dates are usually confirmed around 2 weeks before works begin. Residents and businesses in nearby areas will be notified by letter once a start date is confirmed. If schemes are delayed due to weather or other circumstances, we will write to residents and businesses and ensure further updates are provided.
You can find more information on the types of treatment works on the Pavement and road repair treatment types page.
The work programme is developed in collaboration with our term maintenance contractor Tarmac Kier Joint Venture (TKJV), and our resilience contractors Marlborough Highways and O'Hara Bros Surfacing.
2025/2026 work programme - updated weekly
Road name and postcode | Details of work | Status |
---|---|---|
Alexandra Road, N10 | Road resurfacing - Pert Close to Oak Avenue junction | Awaiting scheduling |
Alexandra Road, NW4 | Road resurfacing - Victoria Road to Finchley Lane | Awaiting scheduling |
Approach Road, EN4 | Road resurfacing - Tewkesbury Close and East Barnet Road | Scheduled to start 15 April 2025 |
Baring Road, EN4 | Road resurfacing - Castlewood Road to Lawton Road (Junction included) | Awaiting scheduling |
Barnet Hill, EN5 | Road resurfacing - Underhill and Potters Lane/West Parade | Awaiting scheduling |
Bohun Grove, EN4 | Pavement patching - 58 Bohun Grove to junction with Ridgeway Avenue | Awaiting scheduling |
Bridge Lane, NW11 | Road resurfacing - outside No. 146 to outside No. 3 | Awaiting scheduling |
Brockley Hill, HA7 | Road patching - Royal National Orthopedic Hospital Access to Pipers Green Lane Junction | Awaiting scheduling |
Burnt Oak Broadway, HA8 | Road resurfacing - From Deansbrook Road to Southbourne Avenue | Awaiting scheduling |
Chase Way, N14 | Pavement patching - 6 Chase Way to 16 Chase Way | Scheduled to start 1 April 2025 |
Church Road NW4 | Road resurfacing - outside no. 63 - Parson Street/Brent Street (Junction partially included) | Awaiting scheduling |
Church Road, NW4 | Pavement patching - Opposite 49 Church Road to Opposite 61 Church Road | Awaiting scheduling |
Church Terrace NW4 | Road resurfacing - North side of Primary School to Gate outside Danbury House | Awaiting scheduling |
Colindeep Lane, NW9 | Road patching - outside McDonald to Junction with The Hyde | Awaiting scheduling |
Colney Hatch Lane, N10 | Pavement resurfacing - Junction From George Crescent to Junction Hallwick Road | Awaiting scheduling |
Colney Hatch Lane N10 | Road resurfacing - Southbound Lane - Opposite George Crescent - Cromwell Road (junction included) | Awaiting scheduling |
Colney Hatch Lane, N10 | Pavement patching - Junction with Wilton Road to Junction with Goodwyn's Vale | Awaiting scheduling |
Cool Oak Lane, NW9 | Pavement patching - Side of 129 West Hendon Broadway to Side of 129 West Hendon Broadway | Awaiting scheduling |
Deans Lane, HA8 | Road patching - WB Lane - Splitter outside John Keble Church to WB Lane - Splitter o/s no.100 | Awaiting scheduling |
Deans Lane, HA8 | Pavement patching - 81 Deans Lane to 93 Deans Lane | Awaiting scheduling |
East Barnet Road, EN4 | Road resurfacing - Welbeck Road & Middle Road | Scheduled to start 16 April 2025 |
East Barnet Road, EN5 | Road resurfacing - Under Rail Bridge & Albert Road | Scheduled to start 11 April 2025 |
East End Road, N3 | Road resurfacing - outside 4 East End Road & St Marylebone Crem Exit | Scheduled to start 7 April 2025 |
Edgeworth Road, EN4 | Road resurfacing - Park Road to Mount Pleasant | Awaiting scheduling |
Edgware Road Slip 1, NW2 | Road patching - Staples Corner Roundabout to A5 Edgware Road S/B mainline | Awaiting scheduling |
Edgware Road Slip 1, NW2 | Pavement patching - Outside 6 to Outside 6 | Awaiting scheduling |
Edgwarebury Lane, HA8 | Pavement patching - 92 Edgwarebury Lane to 68 Edgwarebury Lane | Awaiting scheduling |
Ellesmere Avenue, NW7 | Road patching - Barnet Way to Westmere Drive | Awaiting scheduling |
Elm Close, NW4 | Pavement patching - 5 Elm Close to 7 Elm Close | Awaiting scheduling |
Fenhurst Gardens, HA8 | Pavement resurfacing - Junction From A5 High Street to Junction Green Lane (Both sides of Footway) | Awaiting scheduling |
Finchley Road, NW11 | Pavement resurfacing - From rear of 1-16 Hurstwood Court To Junction Willifield Way (Both Sides of Footway) | Awaiting scheduling |
Friern Barnet Lane, N20 | Road resurfacing - Between Friary Road & Myddleton Park | Awaiting scheduling |
Friern Barnet Road, N11 | Road patching - outside no.19 to Borough Boundary | Awaiting scheduling |
Friern Watch Avenue, N12 | Pavement patching - Junction with High Road to Junction with High Road | Awaiting scheduling |
Golders Green Road, NW11 | Pavement patching - 7 Golders Green Road to 11 Golders Green Road | Awaiting scheduling |
Goldsmith Avenue, NW9 | Pavement resurfacing - From The Junction Of Kingsbury Avenue To Junction The Hyde | Awaiting scheduling |
Gravel Hill, N3 | Pavement patching - Junction with Bibsworth Road to Junction with Regents Park Road | Awaiting scheduling |
Greyhound Hill, NW4 | Pavement patching - 75 Greyhound Hill to 57 Greyhound Hill | Awaiting scheduling |
Greyhound Hill, NW4 | Pavement patching - 20 Greyhound Hill to 16 Greyhound Hill | Awaiting scheduling |
Grove Road, EN4 | Road resurfacing - outside No. 12 to Mount Pleasant | Awaiting scheduling |
Hale Lane, HA8 | Road patching - outside no. 133 to outside no. 139 | Awaiting scheduling |
Hammers Lane, NW7 | Road resurfacing - Shakespeare Road (junction included) - Buckland Close | Awaiting scheduling |
Hermitage Lane, NW2 | Road resurfacing - Elm Terrace & Platt's Lane | Awaiting scheduling |
High Road, N12 | Road resurfacing - Friern Watch Avenue & Derwent Crescent | Awaiting scheduling |
High Road, N3/N12 | Road resurfacing - Glebelands Close & Churchfield Avenue | Awaiting scheduling |
High Road Road, N20 | Road resurfacing - South Bound outside Arka House & outside Service Station | Scheduled to start 17 April 2025 |
Holcombe Hill, NW7 | Pavement patching - Whole of to Whole of | Awaiting scheduling |
Holders Hill Road, NW4 | Pavement patching - Holders Hill Avenue to 18m South of junction with Holders Hill Avenue | Scheduled to start 1 April 2025 |
Hutton Grove, N12 | Road patching - Ballards lane to Nether Street | Awaiting scheduling |
Lanacre Avenue, NW9 | Road resurfacing - Quakers Course (junction included) to North Acre (junction included) | Awaiting scheduling |
Leslie Road, N2 | Road patching - Church Lane to High Road | Awaiting scheduling |
Lodge Lane, N12 | Pavement patching - 2 Lodge Lane to 2 Lodge Lane | Scheduled to start 22 April 2025 |
Manns Road, HA8 | Pavement patching | Awaiting scheduling |
Meadway, NW11 | Pavement patching - 12 Meadway to Opposite 17 Meadway | Awaiting scheduling |
Midholm Close, NW11 | Road patching - Hill Top to End of Cul de Sac | Awaiting scheduling |
Millway, NW7 | Road resurfacing - No. 30 Busy Bees Nursery to The Broadway | Awaiting scheduling |
Milton Road, NW9 | Pavement patching - Whole of to Whole of | Awaiting scheduling |
Norrice Lea, N2 | Road patching - Linden Lea to Deacons Rise | Awaiting scheduling |
Oakleigh Road North, N20 | Road patching - 5 Oakleigh Mews to Pollard Road | Awaiting scheduling |
Orange Hill Road, HA8 | Pavement patching - 84 Orange Hill Road to 102 Orange Hill Road | Awaiting scheduling |
Osidge Lane, N14 | Pavement patching - 180 Osidge Lane to 150 Osidge Lane | Awaiting scheduling |
Priestley Way, NW9 | Pavement patching - Junction with West Hendon Broadway to Junction with West Hendon Broadway | Awaiting scheduling |
Prince Of Wales Close, NW4 | Road resurfacing - Church End to End of Prince of Wales Close | Awaiting scheduling |
Purley Avenue, NW2 | Pavement patching - 44 Purley Avenue to 34 Purley Avenue | Awaiting scheduling |
Queens Road, NW4 | Road resurfacing - Wykeham Road - Central Island/End of Queens Parade | Awaiting scheduling |
Simmons Way, N20 | Pavement resurfacing - Junction from Russell Road to Junction Barfield Avenue | Scheduled to start 1 April 2025 |
Somercoates Close, EN4 | Pavement patching - Junction with Northfield Road to Junction with Northfield Road | Awaiting scheduling |
Somerton Road, NW2 | Pavement patching - Junction with Claremont Road to Opposite 11 Somerton Road | Scheduled to start 7 April 2025 |
St Davids Place, NW4 | Pavement patching - 6 St David's Place to 9 St David's Place | Scheduled to start 8 April 2025 |
St Margarets Avenue, N20 | Road resurfacing - High Street to Totteridge Lane | Awaiting scheduling |
Stanhope Road, N12 | Pavement patching - 53 Stanhope Road to 39 Stanhope Road | Awaiting scheduling |
Station Road, NW4 | Road resurfacing - Talbot Crescent (Junction Included) - outside no.107 | Awaiting scheduling |
Sturgess Avenue, NW4 | Road resurfacing - No. 109 - Dallas Road | Awaiting scheduling |
The Drive, HA8 | Pavement patching - Side of 56 Edgwarebury Lane to Side of 56 Edgwarebury Lane | Scheduled to start 22 April 2025 |
The Hyde, NW9 | Road resurfacing - From Southbourne Avenue to Asda Colindale Superstore | Awaiting scheduling |
The Hyde, NW9 | Road resurfacing - From Colindeep Lane to Wakemans Hill Avenue | Awaiting scheduling |
The Ridgeway, NW11 | Pavement patching - Junction with Hodford Road to Opposite 2 The Ridgeway | Awaiting scheduling |
The Ridgeway, NW7 | Pavement patching - Outside Kirkstall House to Junction with Holcombe Hill | Awaiting scheduling |
The Riding, NW1 | Pavement patching - Outside 7 The Riding to Opposite St Michaels Court | Awaiting scheduling |
The Vale, NW11 | Pavement resurfacing - From The junction Of Claremont Road to junction Hendon Way | Scheduled to start 1 April 2025 |
The Vale, NW11 | Pavement patching - 30 The Vale to 48 The Vale | Awaiting scheduling |
Vivian Road, NW4 | Road resurfacing - outside side of 157a Audley Road - Station Road | Awaiting scheduling |
Warwick Road, EN5 | Road resurfacing - Station Road to Leicester Road | Awaiting scheduling |
Water Brook Lane, NW4 | Pavement patching - Traffic island junction with Queen's Road to Traffic island junction with Queen's Road | Awaiting scheduling |
Wellhouse Lane, EN5 | Road resurfacing - Bus Stop Opposite Barnet Hospital - Wellside Close (Junction Included) | Awaiting scheduling |
Westbury Road, N12 | Road resurfacing - Holden Road to Westbury Grove (Junction included) | Awaiting scheduling |
Western Parade, EN5 | Pavement patching - Junction with Great North Road to Entrance to Filling Station | Awaiting scheduling |
Wolsey Grove, HA8 | Pavement patching - Junction with Cressingham Road to Junction with Horsecroft Road | Awaiting scheduling |
Wood Street, EN5 | Pavement patching - Junction with Cattley Close to Junction with Manor Road | Awaiting scheduling |
Woodfield Avenue, NW9 | Pavement patching - Junction with New Way Road to 45 Woodfield Avenue | Awaiting scheduling |
York Road, EN5 | Road resurfacing - Longmore Avenue to Parking Lot opposite No. 35 | Awaiting scheduling |