Programmed road and pavement works
On this page
Each year, a number of Barnet's roads and pavements are selected for repair based on their condition.
- Our programme of works for 2025/2026 was agreed by Barnet Council's Cabinet on 5 February 2025.
- Our programme of works for 2024/2025 was agreed by Barnet Council's Cabinet on 12 March 2024.
Start dates are usually confirmed around 2 weeks before works begin. Residents and businesses in nearby areas will be notified by letter once a start date is confirmed. If schemes are delayed due to weather or other circumstances, we will write to residents and businesses and ensure further updates are provided.
You can find more information on the types of treatment works on the Pavement and road repair treatment types page.
The work programme is developed in collaboration with our term maintenance contractor Tarmac Kier Joint Venture (TKJV), and our resilience contractors Marlborough Highways and O'Hara Bros Surfacing.
2025/2026 work programme - updated weekly
Road name and ward | Details of work | Status |
---|---|---|
Alexandra Road, Hendon | Road resurfacing | Awaiting scheduling |
Approach Road, East Barnet | Road resurfacing | Awaiting scheduling |
Baring Road, East Barnet | Road resurfacing | Awaiting scheduling |
Barnet Hill, Barnet Vale/Underhill | Road resurfacing | Awaiting scheduling |
Bohun Grove, East Barnet | Pavement patching | Awaiting scheduling |
Bridge Lane, Golders Green | Road resurfacing | Awaiting scheduling |
Brockley Hill, Edgware | Road patching | Awaiting scheduling |
Brookhill Road, East Barnet | Road resurfacing | Awaiting scheduling |
Chase Way, Brunswick Park | Pavement patching | Awaiting scheduling |
Church Road, Hendon | Road resurfacing | Awaiting scheduling |
Church Road, Hendon | Pavement patching | Awaiting scheduling |
Church Road, Hendon | Pavement patching | Awaiting scheduling |
Church Terrace, Hendon | Road resurfacing | Awaiting scheduling |
Colindeep Lane, Colindale South | Road patching | Awaiting scheduling |
Colney Hatch Lane, Friern Barnet | Road resurfacing | Awaiting scheduling |
Colney Hatch Lane, Friern Barnet | Pavement resurfacing | Awaiting scheduling |
Colney Hatch Lane, Friern Barnet | Pavement patching | Awaiting scheduling |
Colney Hatch Lane, Friern Barnet | Pavement patching | Awaiting scheduling |
Cool Oak Lane, West Hendon | Pavement patching | Awaiting scheduling |
Deans Lane, Edgware | Road patching | Awaiting scheduling |
Deans Lane, Edgware | Pavement patching | Awaiting scheduling |
East Barnet Road, East Barnet | Road resurfacing | Awaiting scheduling |
East Barnet Road, East Barnet | Road resurfacing | Awaiting scheduling |
East End Road, Finchley Church End | Road resurfacing | Awaiting scheduling |
Edgeworth Road, East Barnet | Road resurfacing | Awaiting scheduling |
Edgware Road Slip Road, Cricklewood | Road patching | Awaiting scheduling |
Edgware Road Slip Road, Cricklewood | Pavement patching | Awaiting scheduling |
Edgwarebury Lane, Edgware | Pavement patching | Awaiting scheduling |
Ellesmere Avenue, Edgwarebury | Road patching | Awaiting scheduling |
Elm Close, Hendon | Pavement patching | Awaiting scheduling |
Fernhurst Gardens, Edgware | Pavement resurfacing | Awaiting scheduling |
Finchley Road, Golders Green | Pavement resurfacing | Awaiting scheduling |
Friern Barnet Lane, Whetstone | Road resurfacing | Awaiting scheduling |
Friern Barnet Road, Brunswick Park | Road patching | Awaiting scheduling |
Friern Watch Avenue, Woodhouse | Pavement patching | Awaiting scheduling |
Garden City/ Manns Road, Edgware | Pavement patching | Awaiting scheduling |
Golders Green Road, Childs Hill | Pavement patching | Awaiting scheduling |
Goldsmith Avenue, West Hendon | Pavement resurfacing | Awaiting scheduling |
Gravel Hill, Finchley Church End | Pavement patching | Awaiting scheduling |
Greyhound Hill, Hendon | Pavement patching | Awaiting scheduling |
Greyhound Hill, Hendon | Pavement patching | Awaiting scheduling |
Grove Road, East Barnet | Road resurfacing | Awaiting scheduling |
Hale Lane, Edgware | Road patching | Awaiting scheduling |
Hammers Lane, Mill Hill | Road resurfacing | Awaiting scheduling |
Hermitage Lane, Childs Hill | Road resurfacing | Awaiting scheduling |
High Road, West Finchley/Woodhouse | Road resurfacing | Awaiting scheduling |
High Road, Whetstone | Road resurfacing | Awaiting scheduling |
High Road, Woodhouse | Road resurfacing | Awaiting scheduling |
Highfield Avenue, Golders Green | Road resurfacing | Awaiting scheduling |
Holcombe Hill, Mill Hill | Pavement patching | Awaiting scheduling |
Holders Hill Road, Finchley Church End | Pavement patching | Awaiting scheduling |
Hutton Grove, West Finchley | Road patching | Awaiting scheduling |
Lanacre Avenue, Colindale North | Road resurfacing | Awaiting scheduling |
Leslie Road, East Finchley | Road patching | Awaiting scheduling |
Lodge Lane, West Finchley | Pavement patching | Awaiting scheduling |
Meadway, Garden Suburb | Pavement patching | Awaiting scheduling |
Midholm Close, Garden Suburb | Road patching | Awaiting scheduling |
Millway, Mill Hill | Road resurfacing | Awaiting scheduling |
Milton Road, West Hendon | Pavement patching | Awaiting scheduling |
Norrice Lea, Garden Suburb | Road patching | Awaiting scheduling |
Oakleigh Road North, Whetstone | Road patching | Awaiting scheduling |
Orange Hill Road, Burnt Oak | Pavement patching | Awaiting scheduling |
Osidge Lane, Brunswick Park | Pavement patching | Awaiting scheduling |
Priestley Way, West Hendon | Pavement patching | Awaiting scheduling |
Prince Of Wales Close, Hendon | Road resurfacing | Awaiting scheduling |
Purley Avenue, Childs Hill | Pavement patching | Awaiting scheduling |
Queens Road, Hendon | Road resurfacing | Awaiting scheduling |
Simmons Way, Whetstone | Pavement resurfacing | Awaiting scheduling |
Somercoates Close, East Barnet | Pavement patching | Awaiting scheduling |
Somerton Road, Childs Hill | Pavement patching | Awaiting scheduling |
St Davids Place, West Hendon | Pavement patching | Awaiting scheduling |
St Margarets Avenue, Whetstone | Road resurfacing | Awaiting scheduling |
Stanhope Road, Woodhouse | Pavement patching | Awaiting scheduling |
Station Road, West Hendon | Road resurfacing | Awaiting scheduling |
Sturgess Avenue, West Hendon | Road resurfacing | Awaiting scheduling |
The Drive, Edgware | Pavement patching | Awaiting scheduling |
The Hyde, Colindale South | Pavement patching | Awaiting scheduling |
The Ridgeway, Childs Hill | Pavement patching | Awaiting scheduling |
The Ridgeway, Mill Hill | Pavement patching | Awaiting scheduling |
The Riding, Childs Hill | Pavement patching | Awaiting scheduling |
The Vale, Childs Hill | Pavement resurfacing | Awaiting scheduling |
The Vale, Childs Hill | Pavement patching | Awaiting scheduling |
Vivian Avenue, West Hendon | Road resurfacing | Awaiting scheduling |
Warwick Road, Barnet Vale | Road resurfacing | Awaiting scheduling |
Water Brook Lane, Hendon | Pavement patching | Awaiting scheduling |
Wellhouse Lane, High Barnet/Underhill | Road resurfacing | Awaiting scheduling |
Wellhouse Lane, High Barnet/Underhill | Road resurfacing | Awaiting scheduling |
Westbury Road, Totteridge & Woodside/West Finchley | Road resurfacing | Awaiting scheduling |
Western Parade, Barnet Vale | Pavement patching | Awaiting scheduling |
Wolsey Grove, Burnt Oak | Pavement patching | Awaiting scheduling |
Wolsey Grove, Burnt Oak | Pavement patching | Awaiting scheduling |
Wood Street, High Barnet | Pavement patching | Awaiting scheduling |
Woodfield Avenue, Colindale South | Pavement patching | Awaiting scheduling |
York Road, Barnet Vale | Road resurfacing | Awaiting scheduling |
2024/2025 work programme - updated weekly
Road name and postcode | Details of work | Status |
---|---|---|
Abbots Road, HA8 | Pavement resurfacing - Cardinal Close to Orange Hill Road (L) | Completed |
Alston Road, EN5 | Pavement patching - From Side of no.2 Falkland Rd to Entrance to Alston Court / L | Completed |
Alverstone Avenue, EN4 | Road resurfacing - From O/S no.7 to O/S no. 10a | Completed |
Amber Grove, NW2 | Road patching - From Prayle Grove to End | Completed |
Ashburnham Close, N2 | Pavement resurfacing - Stanley Road to End (B) | Completed |
Ballards Lane, N12 | Pavement patching - From o/s no.382 to opposite no. 751 High Road (R) | Completed |
Baring Road, EN4 | Pavement patching - From O/s No. 9 Baring Road to O/s no.7 Baring Road / R | Completed |
Barnet Gate Lane, EN5 | Road resurfacing - From Barnet Road to May's Lane | Completed |
Barnet Road, EN5 | Pavement patching - From Kerri Close junction to Pine Lodge Driveway / L | Completed |
Barnet Road, EN5 | Road patching - From 30MPH before B552, Hendon Wood Lane to 110m past Kerri Close | Completed |
Barnet Road, EN5 | Road patching - From start of Splitter Island to 30MPH before B552, Hendon Wood Lane | Completed |
Barnet Road, EN5 | Road resurfacing - From 100M East of Kerri Close to end of splitter island, Wood Street | Completed |
Bellevue Road, N12 | Road patching - Friern Barnet Road to The Crescent | Completed |
Broadhurst Avenue, HA8 | Road patching - Broadfields Avenue to O/S 40 | Completed |
Brockley Hill, HA7 | Road resurfacing - Bridge repairs | Completed |
Brunswick Park Road, N11 | Road resurfacing - From Osidge lane (incl. roundabout) to Russell Lane | Completed |
Burnt Oak Broadway, HA8 | Pavement patching - Montrose Avenue to Bridge (L) | Completed |
Burnt Oak Broadway, HA8 | Pavement patching - From O/S No 47 Burnt Oak Broadway to Stag Lane / L | Completed |
Burnt Oak Broadway, HA8 | Road patching - From Deansbrook Road to Southbourne Avenue | Awaiting scheduling |
Church Hill Road, EN4 | Road patching - Parkside Gardens to Stuart Road | Completed |
Claremont Road, EN4 | Road resurfacing - Junction with Clitterhouse Rd to OS School House (inc roundabout) | Completed |
Claremont Road, NW2 | Pavement patching - From Opposite Caney Mews bus stop F (on Claremont Rd) to Opposite Junction with Caney Mews / R | Completed |
Claremont Road, NW2 | Pavement patching - From Opposite bundary of no. 22/23 to Opposite no.26 / L | Completed |
Colindale Avenue, NW9 | Pavement patching - From Opposite Bus Stop CB (Colindale Station) to Lamp Column 23 (approximately) / L | Awaiting scheduling |
Colindeep Lane, NW9 | Road resurfacing - Industial estate to dule carridgeway | Completed |
Colindeep Lane, NW9 | Road resurfacing - outside 95 to | Completed |
Coppetts Road, N10 | Road resurfacing - Left and right hand of side splitter | Completed |
Dale Grove, N12 | Road patching - Dale Grove to Birkbeck Road, access to No.1 Dale Grove | Completed |
Daws Lane, NW7 | Road resurfacing - From Byron Road to Watford Way | Completed |
Deans Lane, HA8 | Pavement resurfacing - From Grange Hill To Hale Close (L) / From West Way To Laneside (L) / From Hale Drive To Rudyard Grove (R) | Completed |
Deansway, N2 | Pavement patching - From O/s No 24 Deansway to O/s No 26 Deansway / L | Completed |
Deansway, N2 | Road patching - From O/S No 5 to O/S No 19 | Completed |
Deansway, N2 | Road patching - From O/S No 2 to No 8 | Completed |
Dollis Road, N3 | Road patching - O/S 15 to Nether Street | Completed |
Eagans Close, N2 | Pavement resurfacing - Market Place to End (B) | Completed |
East End Road, N2 | Pavement patching - From 7m south of Entrance to Ethan Drive to Start of Bus Bay near Buckland House / L | Completed |
East End Road, N3 | Pavement patching - From O/s No. 94 East End Road to O/s No. 114 East End Road / R | Completed |
Eastville Avenue, NW11 | Pavement resurfacing - Leeside Crescent to Grosvenor Gardens (R) | Completed |
Edgware Road Flyover, NW2 | Road patching - Opposite Priestley Way | Completed |
Edgware Road Flyover, NW2 | Road patching - Patch opposite Staples Corner Business Park | Completed |
Edgware Road Flyover, NW9 | Road patching - Outside 100 W Hendon Broadway and on flyover | Completed |
Edgware Road Flyover, NW9 | Road patching - Opposite Brent Park Road to opposite Woolmead Avenue | Completed |
Edgware Road, NW2 | Road patching - End of splitter to Gratton Terrace (Cricklewood Broadway) | Awaiting scheduling |
Edgware Road, NW2 | Pavement patching - Opposite entrance to Shell Garage (no.383) to Pedestrian Guardrail by Geron Way (R) | Completed |
Edgware Road, NW2 | Pavement resurfacing - Geron Way to Opposite Humber Road (R) | Completed |
Esmar Crescent, NW9 | Road resurfacing - From Cool Oak Lane to end of road | Completed |
Fairlawn Avenue, N2 | Pavement resurfacing - High Road to Corner (B) | Scheduled to start: 24 February 2025 |
Fairmead Crescent, HA8 | Road resurfacing - Kenilworth Road Parnell Close | Completed |
Finchley Lane, NW4 | Pavement patching - From Opposite no.34 Finchley Ln to O/s no.47 Finchley Ln / L | Completed |
Finchley Lane, NW4 | Road patching - Linfield Close to A1(T) Great North Way | Awaiting scheduling |
Finchley Road, NW11 | Pavement patching - From Alberon Gardens to Addison Way / R | Completed |
Finchley Road, NW11 | Road patching - Cricklewood Lane to Rodborough Road | Completed |
Finchley Road, NW11 | Road patching - Rodborough Road to North End Road (A502) | Completed |
Fitzjohn Avenue, EN5 | Road resurfacing - From Side of Red Lion Pub to Mays Lane | Completed |
Friern Barnet Lane, N20 | Road resurfacing - From Friary Road to Windsor Court | Completed |
Friern Barnet Road, N11 | Road resurfacing - From Ramsden Road to Carlton Road | Completed |
Frith Court, NW7 | Road patching - From B1462 to Abercorn Road | Completed |
Garratt Road, HA8 | Pavement patching - From O/S No 13 Garratt Road to No 5 (Church Boundary) / R | Completed |
Gervase Road, HA8 | Pavement patching - From Side of no.1 Thirleby Rd to O/s no.13 Gervase Road / R | Completed |
Glebe Crescent, NW4 | Pavement patching - From O/s no.12 Glebe Crescent to O/s no.24/26 Glebe Crescent / L | Completed |
Gloucester Grove, HA8 | Pavement patching - From Montrose Avenue to O/s no.8 Gloucester Grove / R | Completed |
Grahame Park Way, NW9 | Pavement resurfacing - Pedestrian Crossing Point (Opposite Field Mead) to LP39 (L) | Completed |
Great North Road, EN5 | Road resurfacing - From Cherry Hill to Walfield Avenue (Phase 2) | Completed |
Great North Road, EN5 | Road resurfacing - From Joint o/s no. 3 (Borough Boundary) to Beaumont Place | Completed |
Great North Road, EN5 | Road resurfacing - From Station Road to Cherry Hill (Phase 1) | Completed |
Gresham Avenue, N11 | Pavement resurfacing - Bethune Play Area FW junction to Corner of Sports Facility (L) | Completed |
Hadley Green, EN5 | Road resurfacing - From Christ Church Lane to Dury Road | Completed |
Hale Grove Gardens, NW7 | Pavement resurfacing - Hale Grove Garden Footpath (from Hale Grove to railway bridge west face) & Lilley Lane (from Manor Drive to Hale Grove) | Completed |
Hale Lane, HA8 | Pavement resurfacing - Upcroft Avenue to Stoneyfields Lane (L) | Completed |
Hammers Lane, NW7 | Pavement patching - From Between LP20 and LP21/ O/s no.59 Hammers Lane to Approx LP22 / L | Completed |
Hampstead Gardens | Road resurfacing - Finchley road to End (cul-de-sac) | Completed |
Hampstead Way, NW11 | Pavement patching - From Side of 802/806 Finchley Rd (End of Cobbles) to O/S boundary of No 162/160 / L | Completed |
Hampstead Way, NW11 | Pavement patching - From Finchley Road to End of Cobbles / L | Completed |
Hampstead Way, NW11 | Pavement resurfacing - From Wellgarth Road to junction with Turner's Wood / L | Completed |
Hampstead Way, NW11 | Road patching - From Wellgarth Road to Meadway | Completed |
Hartley Avenue, NW7 | Pavement patching - From Millway Medical Centre western Car Park entrance/Hartley Av to O/S Dome House/Hartley Av / L | Completed |
Hayes Crescent, NW11 | Pavement patching - From O/S Boundary of No 8/6 to O/s 2a Adla House / L | Completed |
Helenslea Avenue, NW11 | Pavement patching - From O/s no.1a Helenslea Avenue to Boundary of No 5/7 Helenslea Avenue / L | Completed |
Hendon Lane, N3 | Road resurfacing - from Rawlins close to 109 Hendon Lane | Completed |
Hendon Lane, NW4 | Pavement patching - From Dollis Brook bridge (Hendon Lane) eastern end of Pedestrial Guardrail to Broughton Avenue / L | Completed |
High Road, N12 | Road resurfacing - From A1003 Kingsway to Churchfield Avenue | Completed |
Highwood Hill, NW7 | Road resurfacing - From A5109 Marsh Lane/Highwood Hill to Lawrence Street | Completed |
Hillary Rise, EN5 | Road resurfacing - Kingsmead to end of road | Completed |
Hillside Gardens, EN5 | Pavement patching - From O/s no.91 Hillside Gardens to O/s no.95/97 Hillside Gardens / L | Completed |
Hodford Road, NW11 | Pavement patching - From Approx. corner by side of no.23 Golders Green Rd to Bus stop post GP (Approx) by side of no. 23 Golders Green Rd / R | Completed |
Holders Hill Road, NW7 | Road patching - Thornfield Avenue to Holders Hill Circus roundabout | Completed |
Holne Chase, N2 | Road patching - Winngton Road to Kingsley Way | Completed |
Hoop Lane, NW11 | Pavement patching - From O/s no.25 Hoop Lane to O/s no.19 Hoop Lane / R | Completed |
Kings Drive, HA8 | Road resurfacing - From Joint o/s no. 79 to Oakleigh Gardens | Completed |
Kings Road, EN5 | Pavement patching - From O/s no.3/5 Kings Road to O/s no.9 Kings Road / L | Completed |
Kingsway, N12 | Road resurfacing - From A1003 Woodhouse Road ro A598 Ballards Lane | Completed |
Lawerance Street, N12 | Road resurfacing - The Reddings to Sunnyfields | Completed |
Lawrence Street, NW7 | Pavement patching - From Opp. Victoria Road to Bus Bay opposite Holcombe Court / L | Completed |
Lawton Road, EN4 | Pavement patching - Stonegrove park entrance to Mill Ridge (L) | Completed |
Layfield Crescent, NW4 | Pavement patching - From Layfield Road junction to O/s driveway of No. 54 / L | Completed |
Lichfield Grove, N3 | Pavement resurfacing - Glenhill Close to Boundary of No.2/4 (L) | Completed |
Lyonsdown Road, EN5 | Road resurfacing - From Longmore Avenue to Richmond Road | Completed |
Marsh Lane, NW7 | Road resurfacing - From A1(T) BARNET WAY to o/s no 51 | Completed |
Middleway, NW11 | Road patching - From O/S No 34 to Thornton Way | Completed |
Milespit Hill, NW7 | Pavement patching - From The Willows no.79 to O/S No 83 / L | Completed |
North End Road, NW11 | Pavement resurfacing - The Park to Park Drive (L) | Completed |
North End Road, NW11 | Pavement resurfacing - Hampstead Way to Cinderella Path (R) | Scheduled to start: 7 February 2025 |
North End Road, NW11 | Road resurfacing - From Wellgarth Road to West Heath Drive | Completed |
Northfield Road, EN4 | Pavement patching - From No 80/82 to no. 86/88 | Completed |
Northway Crescent, NW7 | Road patching - From A1 to End (Eastern arm between no. 615-619 and 613 Watford Way) | Completed |
Oak Avenue, N10 | Pavement resurfacing - Sydney Road to Alexandra Road (B) | Awaiting scheduling |
Oakleigh Gardens, HA8 | Road patching - From Green Lane to Oakleigh Gardens inc loop | Completed |
Oakleigh Road North, N20 | Pavement patching - From Oakleigh Road North Railway Bridge (western grass verge) to Oakleigh Road North Railway Bridge (eastern grass verge) / L | Completed |
Oakleigh Road North, N20 | Road resurfacing - From York Way to Ryall's Court access road (Phase 1) | Completed |
Oakleigh Road North, N20 | Road resurfacing - From Ryall's Court to Brunswick Avenue (Phase 2) | Completed |
Orange Hill Road, HA8 | Pavement resurfacing - Blessbury Road to Boston Road (L) | Completed |
Osidge Lane, N14 | Road resurfacing - From Access Road between no.129/131 to Hampden Square | Completed |
Poplar Grove, N11 | Road patching - From Colney Hatch Lane to End | Completed |
Quinta Drive, EN5 | Pavement patching - From LP4 (approx) o/;s Whitings Hill Primary School's sport grounds to LP5 (approx) o/;s Whitings Hill Primary School's sport grounds / R | Completed |
Raleigh Drive, N20 | Road resurfacing - From Oakleigh Road North to Manor Drive | Completed |
Ravensdale Avenue, N12 | Road resurfacing - S/O 860 High Road to O/S 5 | Completed |
Regina Close, EN5 | Pavement resurfacing - Queens Road to End (B) | Completed |
Silkstream Road, HA8 | Pavement resurfacing - Montrose Avenue to Bridge (L) | Completed |
Southover, N12 | Road resurfacing - Northiam to Chanctonbury Way | Completed |
Stapylton Road, EN5 | Pavement resurfacing - Salisbury Road to Union Street (L) | Completed |
Station Approach, EN4 | Road resurfacing - York Road to Station Road | Completed |
Station Road, NW4 | Pavement resurfacing - From Algernon Road to Vaughan Avenue / B | Completed |
Stonegrove, HA8 | Pavement patching - From Regents Court Entrance to Pedestrian Crossing / L | Completed |
Stonegrove, HA8 | Pavement resurfacing - Stonegrove park entrance to Mill Ridge (L) | Completed |
Stonegrove, HA8 | Road resurfacing - From Surface joint o/s no. 52 to Station Road | Completed |
Sutherland Close, EN5 | Pavement resurfacing - Manor Road to End (B) | Completed |
Tapster Street, EN5 | Road patching - Moon Lane to high Street | Completed |
Temple Fortune Lane, NW11 | Road patching - Sheridan Walk to Finchley Road | Completed |
The Avenue, EN5 | Pavement patching - From The Drive to O/s no.1-3 The White Lodge / R | Completed |
The Broadway, NW7 | Pavement patching - O/s no.44 The Broadway to O/s no.50/52 The Broadway (R) | Completed |
The Broadway, NW7 | Road resurfacing - From M1 bridge to Bunns Lane / Hale Lane | Completed |
The Hyde, NW9 | Pavement patching - From Behind no.24 Southbourne Court (opposite side) to Behind no.4 Southbourne Court (opposite side) / L | Completed |
The Hyde, NW9 | Road patching - End of splitter to start of splitter at Hyde estate lights | Awaiting scheduling |
The Hyde, NW9 | Road patching - Kingsbury Road to start of splitter at lights at Hyde estate supermarket entrance | Awaiting scheduling |
The Hyde, NW9 | Road resurfacing - From Southbourne Avenue to Asda Colindale Superstore | Awaiting scheduling |
The Hyde, NW9 | Road resurfacing - From Colindeep Lane to Wakemans Hill Avenue | Awaiting scheduling |
The Ridgeway, NW7 | Pavement resurfacing - From no.2a Rushden Gardens to Watch Tower House (200m north of 2a Rushden Gardens) | Completed |
The Ridgeway, NW7 | Road resurfacing - From High Street to St Vincent Lane | Completed |
The Vale, NW11 | Pavement patching - From O/S No. 107/105 to O/S No. 97/95 / L | Completed |
The Vale, NW11 | Pavement resurfacing - Wayside to The Ridgeway (L) | Completed |
The Vale, NW2 | Road patching - Dunstan Road to The Ridgeway | Completed |
Thirleby Road, HA8 | Pavement patching - From Montrose Avenue to Opposite No 56 Thirleby Rd / R | Completed |
Thirleby Road, HA8 | Road patching - Montrose Avenue to Gervase Road | Completed |
Totteridge Common, N20 | Road resurfacing - From Hendon Wood Lane Jnct (west side) to Hendon Wood Lane Jnct (east side) | Completed |
Totteridge Village, N20 | Road resurfacing - From The Close to O/s no. 18 | Completed |
Varley Parade, NW9 | Road resurfacing - From A5 Edgware Rd to Woodfield Avenue | Completed |
Watling Avenue, HA8 | Road patching - Eversfield Gardens to Cressigham Road | Completed |
West Hendon Broadway Slip 2, NW9 | Road patching - From Brent Park Road to Staples Corner West | Completed |
West Hendon Broadway, NW9 | Road patching - end of splitter to Ramsey Close | Awaiting scheduling |
Wilberforce, NW2 | Road patching - Herbert Road to Station Road | Completed |
Willifield Way, NW11 | Road resurfacing - From Asmuns Hill to Temple Fortune Hill | Completed |
Wood Street, EN5 | Pavement patching - From Cattley Close to Boundary between Union St/ no.53 Wood St / R | Completed |
Wood Street, EN5 | Road resurfacing - From CHURCH PASSAGE to A1000 HIGH STREET | Completed |
Woodside Avenue, N12 | Road resurfacing - Woodside Grange Road to Woodside Park Road | Completed |
Woolmead Avenue, NW9 | Road patching - From Cool Oak Lane to End | Completed |